Yukon Water Board approves new 20-year licence for Whitehorse dam

Yukon Energy’s hydroelectric facility in Whitehorse, in May. The Yukon Water Board this week issued its approval of a new 20-year licence for the dam. (Paul Tukker/CBC)

Decision was last major hurdle for Yukon Energy to keep operating the contentious facility

The Yukon Water Board has approved a new, 20-year operating licence for Yukon Energy’s hydroelectric dam in Whitehorse. It was the last major hurdle for Yukon Energy in its years-long effort to renew its licence for the facility.

The decision issued by the Water Board this week follows a hearing earlier this month, where regulators heard concerns about the 67-year-old dam’s impacts on fish, water levels, land use and traditional culture.

Yukon Energy’s request for a new 20-year licence was earlier cleared by the Yukon Environmental and Socio-economic Assessment Board. The company now must secure authorization under the federal Fisheries Act.

The decision from the Water Board lays out a list of conditions for how the company must run the facility, including how to manage water levels upstream on Marsh Lake, and also ensure the fish ladder at the dam is operating properly to ensure fish passage.

The Whitehorse fish ladder. (Paul Tukker/CBC)

Through the relicensing process, First Nations and environmental groups expressed serious concerns about the dam’s historical and ongoing impact on fish populations in the Yukon River, in particular chinook salmon.

Among other things, the water licence requires Yukon Energy to submit a new operations and maintenance plan for the fish ladder by the end of the year. The company also has until May to submit an updated operations and maintenance manual, and an updated emergency preparedness plan.

The licence also requires the dam undergo a third-party safety inspection every year and a full safety review of the dam, the Lewes control structure and fishway upstream and the Lewes boat lock every five years. The first such review must be done by November.

Other conditions deal with erosion monitoring, water quality, wetland preservation and fish habitat. They also spell out how Yukon Energy must work with local First Nations on some of its monitoring and management plans.

The water licence is in effect as of Thursday and is set to expire in July 2045.

Related stories from around the North:

Canada: Conservationists, Yukon First Nation say decision on Whitehorse dam could help salmon, CBC News

CBC News

For more news from Canada visit CBC News.

Do you want to report an error or a typo? Click here!

Leave a Reply

Note: By submitting your comments, you acknowledge that Radio Canada International has the right to reproduce, broadcast and publicize those comments or any part thereof in any manner whatsoever. Radio Canada International does not endorse any of the views posted. Your comments will be pre-moderated and published if they meet netiquette guidelines.
Netiquette »

Your email address will not be published. Required fields are marked *